Cogent NetworksCogent Networks Cogent NetworksDriving Innovation, Powering Success. Cogent OS
HOME/SERVICES/DATA CENTRE/DATA CENTRE SERVICES
Service line

From floor plan to commissioning -
every step, one partner.

Design, build, cable, install, test, certify and operate. Delivered by directly-employed, DC-cleared workers working from drawings rather than improvisation.

Cx-L1 TO L5TIA-568 / ISO-IEC 11801 / TIA-942DC-CLEARED CREWSTWO-PERSON RULE
12
Lifecycle steps, each with a deliverable
17
Certified parameters per copper link
19
Hubs for staging and burn-in
L1-L5
Commissioning levels
Proof

What we have already built

Built from scratch
A hyperscale data centre delivered end to end
4,000+
Devices commissioned
400+
Racks set up
Thousands of m
Cabling installed and certified
20
Data halls commissioned

Delivered by our own DC-cleared workers, on Cogent OS, under change control - floor plan to final commissioning.

The proposition

Data centre work is unforgiving

The window is fixed, the site rules are absolute, and a cabling shortcut taken in week one is still visible in year five. There is no version of this work where improvisation is cheaper than drawings.

So we design first. Our design team produces the full pack - floor plans, data-point schedules, rack layouts and elevations, power budgets and port maps - and the build is executed from those drawings. Crews arrive knowing which cable goes to which port, in which cabinet, at which U position, before a single cable is pulled.

The result is an as-built pack at handover that matches reality, because the evidence was captured as the work happened rather than reconstructed afterwards. Every rack, run, serial and test result lands in Cogent OS against the asset register.

Technical lifecycle

Twelve steps, twelve deliverables

Each step closes with a document, not a verbal handover. The pack that accumulates is the handover pack.

01
Site survey
Floor, power, cooling, containment and access surveyed. Deliverable: survey report with constraints and risks.
02
Design
Target layout, capacity and topology agreed against the brief. Deliverable: design pack and bill of materials.
03
Cable routing
Trunk runs, containment paths, riser positions and segregation from power. Deliverable: routing plan.
04
Data points
Outlet positions numbered and scheduled per zone. Deliverable: data-point schedule and patch allocation.
05
Rack layout
Row and cabinet positions, aisle orientation, containment. Deliverable: rack layout plan and elevations.
06
Power
Per-cabinet kW budget, A and B feeds, socket schedule, headroom. Deliverable: power design and socket schedule.
07
Build & fit-out
Containment, cabinets, PDUs, basket and tray, labelling scheme. Deliverable: fit-out completion record.
08
Rack & stack
Receive, mount, connect, label and power-on test per elevation. Deliverable: U-by-U as-built inventory.
09
Cabling
Copper and fibre installed, dressed, labelled and certified. Deliverable: test results per link.
10
Power & cooling
Feed discipline, PDU allocation, airflow management and blanking. Deliverable: power and airflow verification.
11
Configuration
Device configuration loaded and verified against the design. Deliverable: configuration baseline and backups.
12
Commissioning
Cx levels one to five including integrated systems testing at full load. Deliverable: Cx results and handover pack.
Design services

Floor plan to rack elevation

Five documents carry a data centre build. They are produced before mobilisation and updated as-built at handover, so the drawing and the room agree.

FLOOR DESIGN · CABLE ROUTING PLANCN-EL-100 · REV A
Floor design cable routing plan: main trunk on basket tray, branch routes, containment and riser routes with floor boxes and wall penetrations across offices, open plan, meeting, lab and comms room
Trunk runs on basket tray with branch drops to each zone and a riser position for vertical distribution. Containment routes, fill capacity and segregation from power are fixed at design stage.
FLOOR DESIGN · DATA POINT PLANCN-EL-101 · REV A
Floor design data point plan: numbered single and dual data outlets, wireless access points, floor boxes and patch panel location per zone
Every outlet position numbered and scheduled per zone before install, so the cable schedule, patch panel allocation and labelling scheme all derive from one document.
SERVER ROOM DESIGN · RACK LAYOUT PLANAS BUILT
Annotated data hall row: numbered cabinets R11 to R110 with row-end PDU A and PDU B, cold aisle feed from perforated floor tiles and hot aisle discharge
Numbered cabinet positions with hot and cold aisle orientation, overhead containment and A/B PDU placement at row ends. Layout is set for airflow and future growth, not just floor fit.
SERVER ROOM DESIGN · RACK ELEVATION42U · AS BUILT
Annotated 42U rack elevation: patch panels, cable managers, top-of-rack switches, firewall pair, storage shelf, compute, UPS bypass, blanking panels, A and B PDU feeds and reserved growth space
U-by-U placement with cable managers, blanking and reserved growth space. Real elevations carry the client's own naming scheme.
SERVER ROOM DESIGN · POWER CONSUMPTION BUDGETA/B FEEDS · AS BUILT
Annotated row-end PDU pair: busway tap-off feed A and feed B at 400A 415V, PDU A total load 18.6 kW and PDU B 18.9 kW, per-phase load across L1 to L3, breaker allocation per circuit and remaining headroom of 5.4 kW and 5.1 kW
Row-end PDUs on independent busway tap-offs, with per-phase balance and remaining headroom visible on the unit. Breakers are allocated and labelled per cabinet, so the budget is auditable at the panel rather than only on the drawing.

Port-level engineering

Every port, every cable, documented before a single cable is pulled. The port map is the instruction the crew works from and the record the client keeps.

CABLE IDA-END (RACK / U / DEVICE / PORT)B-END (RACK / U / DEVICE / PORT)TYPELENGTH
C-1041R11 / 07 / TOR-A / Gi1/0/1R11 / 01 / PP-A / Port 01Cat6A U/FTP2.1 m
C-1042R11 / 07 / TOR-A / Gi1/0/2R11 / 01 / PP-A / Port 02Cat6A U/FTP2.1 m
C-1043R11 / 08 / TOR-B / Gi1/0/1R11 / 04 / PP-B / Port 01Cat6A U/FTP2.3 m
F-2010R11 / 07 / TOR-A / Up-1R23 / 12 / SPINE-1 / Et1/1OM4 LC-LC duplex18.4 m
F-2011R11 / 08 / TOR-B / Up-1R23 / 13 / SPINE-2 / Et1/1OM4 LC-LC duplex19.1 m

Sample rows shown. A full port map covers every link in the build, cross-referenced to the cable schedule, the patch panel allocation and the labelling scheme. Port-stripping layouts are produced where existing plant is being re-terminated.

PORT MAP · AS INSTALLEDSAME CABLE IDS AS THE SCHEDULE ABOVE
Rack R11 A side as installed: cables C-1041, C-1042 and C-1043 labelled and patched from TOR-A and TOR-B to patch panels PP-A and PP-B, and fibre F-2010 and F-2011 running to the spine switches, each label matching its port map row
The same links, installed. Every cable carries the ID from its port map row, so a fault can be traced from the schedule to the physical patch without opening a drawing - and the as-built record is the schedule with nothing changed.
Rack management

Survey and audit discipline

An audit that changes the thing it is auditing is worthless. Our standing survey law is simple: never touch a device or a cable during a survey. Observe, photograph, record, report - then raise the change if something needs doing.

Surveys use a fixed template so two crews in two countries produce comparable output: U-by-U front and rear inventory, manufacturer, model and serial capture, PDU and power-socket schedule, grounding and lock checks, and a photograph of any device not showing a green status LED.

Everything lands in Cogent OS against the asset register, so the audit becomes the CMDB baseline rather than a spreadsheet that ages in a folder.

U-by-U inventory

Front and rear, every U accounted for - occupied, blanked or free - with position recorded against the cabinet.

Asset capture

Manufacturer, model and serial captured per device and written to the asset register, not transcribed later.

Power schedule

PDU inventory and socket-by-socket allocation, including which feed each device draws from.

Grounding & locks

Bonding and earthing verified, cabinet locks and door state checked and recorded.

Non-green-LED photo rule

Any device not showing a healthy status indicator is photographed and flagged, whether or not it is in scope.

Never touch

No device, cable or breaker is moved during a survey. Findings become change records, not on-the-spot fixes.

Structured cabling

Standards, and the craft on top of them

We install to ANSI/TIA-568 and ISO/IEC 11801: multi-vendor generic cabling carrying voice and data, defined subsystems, specified connector and pin assignments, topology and distance rules, a design life beyond ten years, backward compatibility and uniform documentation.

Why the standard matters commercially

A generic cabling system is vendor-independent, so you are not locked to the equipment brand that happened to be current when the room was built. Defined subsystems and distance rules mean the plant supports the next two generations of active kit, and uniform documentation means the next engineer can read it.

The practical test is whether a link certifies. Standards compliance is not a claim on a datasheet; it is a measured result per link, signed and dated.

Every copper link, 17 parameters

Each permanent link up to 90 m is tested and certified against the full parameter set, with results issued per link:

01Wire map02Length03Propagation delay04Delay skew05DC loop resistance06DC resistance unbalance07DC resistance unbalance between pairs08Insertion loss09NEXT10PS NEXT11ACR-N12PS ACR-N13ACR-F14PS ACR-F20Return loss16TCL17ELTCTL

Fibre links are certified by OTDR trace plus optical loss test set. Certification results form part of the handover pack and the warranty position on the plant.

The cabling dress code

A documented standard applied identically in every hall and every country - because dressing and labelling are what make a room maintainable five years after handover. Every cable, device and port is label-printed to the client's scheme where one exists, or to ours where it does not.

Fibre management and labelling in a live hall
Copper trunk discipline on containment
Patch labelling and port identification

What a dressed rack looks like

The discipline in the figure is what separates a rack that can be worked on from one that has to be unpicked.

Cable managers
Vertical and horizontal, so bundles turn at a controlled radius
Data patch panels
Numbered and labelled to the port map, front and rear
Voice patch panels
Separated from data, terminated to the same standard
Fibre patch panel
Trays with slack management and minimum bend radius held
Horizontal management
Every U change routed, never crossing the cabinet face
Power cabling
A and B feeds separated and dressed away from copper runs
Installation standard

Crews, supervision and safety

Experienced crews install network devices and servers to a documented standard: mount, connect, label, power-on test. Nothing is signed off on the basis that it looked right.

Every deployment runs under an on-site project manager who supervises against the initial design rather than against the crew's judgement on the day. Where the room does not match the drawing, that is a change record and a decision - not a quiet deviation discovered at commissioning.

The project manager also owns safety: PPE discipline, working-at-height controls, method statements and risk assessments per visit, permit compliance, and incident handling and reporting. On a live floor those are not administrative overheads; they are the reason the operator lets us back in.

STEP 01

Mount

To elevation, at the specified U, with correct rails and cage nuts, load-checked.

STEP 02

Connect

To the port map, with cable type and length as designed, dressed as installed.

STEP 03

Label

Every cable, device and port printed to the agreed scheme, both ends.

STEP 04

Power-on test

Verified against expected state, with any non-green indicator photographed and raised.

Operations

Once the hall is live

Build is one engagement. Most clients keep us for the operational bands below, delivered by the same cleared workers who built the room.

Field services & IMAC/D in the DC

Reactive break-fix and lifecycle moves inside the hall, under change control with two-person discipline on production-affecting work.

·Component and node swaps·Disk and media handling under custody·Rack-level installs, moves and removals·Change windows honoured strictly

Data centre L2 support

Hands-on technical support beyond remote scope: diagnosis, configuration to procedure, firmware and structured fault isolation.

·Guided and independent diagnosis·Configuration to documented procedure·Firmware and BIOS to change record·Escalation to L3 design authority

Test lab & specialised facility

A controlled environment for build validation, burn-in, firmware baselining and pre-production testing before kit reaches your floor.

·Build and image validation·Burn-in and soak testing·Firmware baseline establishment·Failure reproduction and RMA evidence

Rack logistics from our hubs

Cabinets built, populated, cabled, labelled and burned in at the nearest owned hub, then delivered ready to energise.

·Staged, labelled and serialised·Delivered to the change window·Reduces on-floor time materially·Spares held in-country per SLA

Relocation & migration

Move-group planning with rollback positions, sequenced power-down and power-up, and chain of custody per asset.

·Dependency mapping and move groups·Sequenced shutdown and bring-up·Validation before release to service·Custody record per serial

Secure decommission

Controlled de-rack straight into our ITAD line, with data destruction and a certificate per asset.

·De-rack under custody·NIST 800-88 destruction·Certificate per asset·WEEE reporting and value recovery

NOC

Monitoring and first-line response on infrastructure and network, with alerting integrated into the same ticket model.

·24/7 monitoring and alert triage·Automated ticket creation·Escalation to on-site hands·Trend reporting into QBR

SOC

Security monitoring and incident response alongside the operational picture, rather than in a separate silo.

·Security event monitoring·Incident triage and containment support·Access and audit reporting·Coordination with your own SOC
Dispatch

One process, inside the operator's rules

YOUR TEAM
01
Raise
Ticket, project task or scheduled works with site reference.
06
Sign off
Evidence and certification accepted in the portal.
COGENT OS
02
Entitle & clear
Site, contract and worker clearance validity checked; expired credentials block dispatch.
03
Match
DC-cleared worker matched on skill, induction currency and travel time.
07
Bill
Work order billed and asset register updated.
COGENT WORKER
04
Attend
GPS check-in, facility induction confirmed, work performed under MOP and SOP.
05
Evidence
Worksheet, photographs, serials and test certificates captured.
OUTCOME
Logged
One queue, SLA clock running.
Permitted
Only cleared workers reach the floor.
To standard
Procedure followed, not improvised.
Evidenced
Certificates on the asset record.
Auditable
Operator and client can both verify.

Production-affecting work runs against an approved RFC through change advisory board approval, with the two-person rule applied where the site or change class requires it.

Value beyond scope

Three things clients tell us they did not expect

Rack design expertise

Layout is optimised for performance, heat dissipation, tidiness and future growth - not just for fitting the equipment in. Reserved U space, blanking discipline and cable-manager placement are design decisions, and they are the difference between a cabinet you can work in and one you fight.

Third-party coordination

We manage the other vendors around the project - cabling contractors already appointed, OEM engineers, the operator's own facilities team, mechanical and electrical contractors - so you have one point of contact rather than arbitrating between suppliers on the critical path.

L3 design authority

Certified senior workers across major network, server and wireless platforms are available for solution design and urgent escalation. That means a design question does not wait for a vendor SLA, and a production escalation reaches someone with authority rather than someone reading a script.

Proof

A delivered engagement

CASE STUDY · FINANCIAL SERVICES · UNITED KINGDOM · TURN-KEY OFFICE AND COMMS ROOM
183
Data points installed and certified
12
Access points, survey to validation
20 days
Turn-key, survey to handover

A financial services client took 5,000 square metres of new office space in London for more than 100 users, with a fixed occupation date and no IT presence on the ground. The requirement was everything: cabling design, structured cabling, a wireless survey and deployment, and the network built and working.

We surveyed and produced the design pack first - cable routing plan, data-point schedule for 183 outlets, comms room rack layout and elevation, and the power budget. Delivery then ran in three phases: trunking and cable pulling to the routing plan, termination and dressing to the cabling dress code with every link certified, then finalisation - network configuration, wireless validation survey against the design, labelling and the as-built handover pack.

The site was handed over turn-key in 20 days from survey to acceptance, with certification results per link, an as-built pack matching the room, and the asset register loaded into Cogent OS so the estate was documented from day one rather than reconstructed later.

Anonymised by agreement. Client names available under NDA.

Standards & governance

What we work to

TIA-942
Data centre design and infrastructure
BICSI-002
Design and implementation best practice
BS EN 50600
European data centre facility standard
ANSI/TIA-568
Structured cabling
ISO/IEC 11801
Generic cabling for customer premises
Uptime Tier I-IV
Availability and topology classification
Two-person rule
On production-affecting works
CAB / RFC
Change control on every production change

Governance on site is as documented as the engineering: dress code, facility inductions per worker with tracked expiry, permits and method statements per visit, escorted access where the operator requires it, and photographic evidence against the standard for every task.

Service levels

PRIORITYDEFINITIONRESPONSETARGET RESOLUTIONWINDOW
P1 - CriticalProduction hall, feed or core network affected15 minutes4 hours24/7/365
P2 - HighRedundancy lost or a rack group degraded30 minutes8 hours24/7/365
P3 - MediumSingle device or non-redundant component failed2 hoursNext business dayBusiness hours
P4 - LowPlanned works, IMAC batch, scheduled audit8 hoursTo agreed scheduleBy arrangement
Change windowProduction-affecting works under approved RFCBooked in advanceInside the agreed windowNights and weekends as required

Measured in Cogent OS against the operator's site calendar. Production-affecting work is never performed outside an approved change window, regardless of priority - the escalation path in that case is to the change process, not around it.

On site

The environment we work in

data hall cold aisle
cabling close-up
FAQ

Questions buyers ask

Can you work in a live hall?

Yes, and most of our work is in live environments. It is governed rather than casual: production-affecting tasks run against an approved RFC through change advisory board approval, inside a booked window, with the two-person rule applied where the site or change class demands it. Surveys are non-invasive by rule - we do not touch a device or cable during an audit.

How do you handle clearances and site inductions?

Induction and clearance validity is held per worker in Cogent OS with expiry dates, and dispatch is blocked against an expired credential - so access is never the reason a window is missed. For operators with their own vetting requirements we maintain a dedicated pool of cleared workers for those facilities rather than sending whoever is nearest.

Can cutovers run out of hours?

Yes, and for live halls they usually must. Night and weekend windows are planned into the programme from the start, with the crew, the parts and the rollback position all booked to the window rather than arranged on the night. Out-of-hours cover is priced by window explicitly rather than averaged into a day rate.

What as-built documentation do we receive?

The design pack updated to as-built: cable routing and data-point plans, rack layout and U-by-U elevations, power and socket schedule, the full port map, certification results per copper and fibre link, commissioning results by level, and the asset register with serials. It is issued in portable formats you own, and loaded into the CMDB if we operate the estate.

Is there a warranty on the cabling plant?

Yes. Installation workmanship is warranted, and where the engagement uses a manufacturer's components to their specification, the extended system warranty available on that plant is registered on your behalf. Certification results per link are what make that warranty claimable, which is another reason every link is tested rather than sampled.

Related

Other service lines in this practice

Server & AI ComputePractice overview

Got a hall to build, or an estate to move?

Tell us the floor, the capacity and the window. We will come back with the design approach, the crewing plan and the commissioning schedule.

Get a Quote Talk to an expert
+44 20 3936 1085 · INFO@COGENTNETWORKS.COM